Team area not listing as a drop down for the traceability view for RQM 4.0.2
Hi
Product: RQM V 4.0.2
OS : Linux Database Server (AIX) : DB2 v9.1.0.7 The CLM application was upgraded from 3.0.1.1 to 4.0.2 We were expecting the team area to be listed as drop down in the Traceability view as updated in jazz.net article, but it does not list.
https://jazz.net/downloads/rational-quality-manager/releases/4.0.1?p=news#team_column
Appreciate your inputs on this.
Thanks
|
One answer
Go to Admin->Manage Project Properties and click on Team Areas and Timelines.
Select 'Enable team areas and support for multiple timelines'. This should display the team areas. Best Regards Rajat |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.