Lewis Tsao (2174962) | asked May 28 '13, 9:33 a.m.
We have a "story" planned for "Sprint 1" and children tasks, some are "Sprint 1" and others are in "Backlog". Don't ask why, it just is.

In the plan view viewlet we have "Project -> current project", "Plan -> Sprint 1 plan" "Plan View -> Taskboard"

On the task board all the "Sprint 1 " items are displayed correctly with, but we also have blank place holders for tasks planned for backlog, is this correct behaviour?

It is possible not to display the place holders?



Comments
Aradhya K commented Jun 05 '13, 2:18 a.m.
JAZZ DEVELOPER

Hi Lewis 

Thanks for getting the clear steps for reproducing the problem.
I was able to reproduce this issue on the latest RTC server as well.
I will create a defect for the same and post here.


Accepted answer


permanent link
Aradhya K (1.4k44345) | answered Jun 05 '13, 10:42 a.m.
JAZZ DEVELOPER
Taskboard views in Dashboard show blank work items (267957) is the defect for the issue.
Please track the progress from this link.
Lewis Tsao selected this answer as the correct answer