can I export the task estimates in just hours?
I exported a list of all tasks of my sprint into a spreadsheet with their estimates. I wouldlike to sum up the estimates, but days and hours do not sum up :(
The sprint burndown does give me the sum of them too, but th enumber doesn't seem to be right:
mine sums up to 150, burn down shows 128
The sprint burndown does give me the sum of them too, but th enumber doesn't seem to be right:
mine sums up to 150, burn down shows 128
One answer
I exported a list of all tasks of my sprint into a spreadsheet with
their estimates. I wouldlike to sum up the estimates, but days and
hours do not sum up :(
The sprint burndown does give me the sum of them too, but th enumber
doesn't seem to be right:
mine sums up to 150, burn down shows 128
If you use the work item export wizard (RTC Eclipse UI) to export query
results to a spreadsheet, you have the option to configure individual
attributes. You can configure the Estimate attribute to return its
internal value (milliseconds) and then add up the numbers in the
spreadsheet.
--
Regards,
Patrick