can I export the task estimates in just hours?
I exported a list of all tasks of my sprint into a spreadsheet with their estimates. I wouldlike to sum up the estimates, but days and hours do not sum up :(
The sprint burndown does give me the sum of them too, but th enumber doesn't seem to be right: mine sums up to 150, burn down shows 128 |
One answer
I exported a list of all tasks of my sprint into a spreadsheet with If you use the work item export wizard (RTC Eclipse UI) to export query results to a spreadsheet, you have the option to configure individual attributes. You can configure the Estimate attribute to return its internal value (milliseconds) and then add up the numbers in the spreadsheet. -- Regards, Patrick Jazz Work Item Team |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.