Hi,

I have some test requirements created in Requirements Manager and now I am trying to link those test requiements in the Test Plan but when I open the Requirement Section in the Test plan, all the options of adding new requirements or associating existing test requiements are disabled.

Hasn anyone faced this type of issue or anyone has solution to fix this?

One answer



permanent link
Paul Slauenwhite (8.4k12) | answered May 07 '13, 7:39 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
See the steps 8/9 of http://pic.dhe.ibm.com/infocenter/clmhelp/v3r0m1/topic/com.ibm.rational.test.qm.doc/topics/t_manage_reqs_rm.html.