Iteration Planning problem: Story planned but no estimate...

Hello all,
I have the following problem:
I have a project with Scrum as process template.
I defined an iteration, and an iteration plan for it.
Created a Story, and set it's "Planned For" field to the iteration.
Now I have a "Problems detected" warning, on the iteration plan Overview pane, which when clicked, expands to several messages:
"The work item is planned but has no estimate specified."
I set the Story Points for this Story, and defined child work items (as tasks), and the tasks are estimated.
What am I doing wrong?
Csaba Trucza
I have the following problem:
I have a project with Scrum as process template.
I defined an iteration, and an iteration plan for it.
Created a Story, and set it's "Planned For" field to the iteration.
Now I have a "Problems detected" warning, on the iteration plan Overview pane, which when clicked, expands to several messages:
"The work item is planned but has no estimate specified."
I set the Story Points for this Story, and defined child work items (as tasks), and the tasks are estimated.
What am I doing wrong?
Csaba Trucza
One answer

csaba.trucza wrote:
Nothing ;-) This is actually a bug in our problem checker. I have opened
a defect. Feel free to subscribe.
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/64876
--
Cheers, Johannes
Agile Planning Team
Hello all,
I have the following problem:
I have a project with Scrum as process template.
I defined an iteration, and an iteration plan for it.
Created a Story, and set it's "Planned For" field to the
iteration.
Now I have a "Problems detected" warning, on the iteration
plan Overview pane, which when clicked, expands to several messages:
"The work item is planned but has no estimate specified."
I set the Story Points for this Story, and defined child work items
(as tasks), and the tasks are estimated.
What am I doing wrong?
Nothing ;-) This is actually a bug in our problem checker. I have opened
a defect. Feel free to subscribe.
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/64876
--
Cheers, Johannes
Agile Planning Team