Hi Team,
In my project I have an epic, which exceptionally has children in a different project area. I noticed that this epic doesn't display correctly progress bar for story points and hours - it's still 0/0, although children change their progress.

Epic (project area 1)
---> Story (project area 2)
-------> Task (project area 2)
-------> Task (project area 2)
---> Story (project area 2)
-------> Task (project area 2)
-------> Task (project area 2)
-------> Task (project area 2)

It it because progress calculation doesn't work across project areas? Is there any way to fix it?
Thanks
Robert

Accepted answer


permanent link
Ralph Schoon (63.1k33645) | answered Jun 26 '15, 6:43 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
That is right. It is designed to accumulate within one project area only.
Robert Dumnicki selected this answer as the correct answer