Hi Team,
In my project I have an epic, which exceptionally has children in a different project area. I noticed that this epic doesn't display correctly progress bar for story points and hours - it's still 0/0, although children change their progress.

Epic (project area 1)
---> Story (project area 2)
-------> Task (project area 2)
-------> Task (project area 2)
---> Story (project area 2)
-------> Task (project area 2)
-------> Task (project area 2)
-------> Task (project area 2)

It it because progress calculation doesn't work across project areas? Is there any way to fix it?
Thanks
Robert

0 votes


Accepted answer

Permanent link
That is right. It is designed to accumulate within one project area only.
Robert Dumnicki selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,221

Question asked: Jun 26 '15, 6:25 a.m.

Question was seen: 2,700 times

Last updated: Jun 26 '15, 6:43 a.m.

Confirmation Cancel Confirm