It's all about the answers!

Ask a question

What's the best practice with RQM Test Schedules when migrating to RQM 4.0.1?


Michael Walker (99215201157) | asked Feb 25 '13, 1:34 a.m.
After we migrate customers from RQM 3.0.x to RQM 4.0.1 the Test Schedules no longer exist.  I understand there's a way to migrate the Test Schedules so they'll appear in 4.0.1, but the new process is to create your Timeline and then create Test Schedules based on those iterations.

Is one of these options considered the best practice?  Should we migrate the Test Schedules or just recreate them by creating a Timeline and then created a new Test Schedule that links to the Timeline?

One answer



permanent link
Rajat Singh (59833545) | answered Feb 25 '13, 2:19 a.m.
The test schedules get auto migrated during the upgrade.
You can browse to 'Manage Project Timelines'.
In this page, check the defined timelines and you should find 'Auto Migrated' iteration which should contain all your schedules that were created before the upgrade:

You can set the timeline holding this iteration as your current timeline and continue creating iterations.
Or you could start afresh by creating a new timeline.

Hope this helps!!

Best Regards
Rajat

Comments
Michael Walker commented Feb 25 '13, 4:17 a.m.

Thanks Rajat.  I do see Auto-Migrated now.  Is the Test Schedule supposed to still be populated after the migration or should we be required to recreate them from the Auto-Migrated timeline?


Rajat Singh commented Feb 25 '13, 8:35 a.m.

Test Schedule is supposed to still populate after the migration.

You can refer the below article which explains this in detail:

Best Regards
Rajat

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.