In our RQM we have defined an external resource. As administrator I could check that we had connectivity to the external resource (such resource was used for RFT scripts). The user tried to import test script choosing the external resource and landed into a waiting loop. In the import dialogue the first line is assigned to the plan, in out case it was 'undefined'. After flipping the plan to another plan listed and flipping back to undefined we could connect to the external resource.
Is this a defect ?

0 votes


Accepted answer

Permanent link
Hi Silvia,

Thank you that report this issue.  I have just created defect 88446: Infinite waiting loop when browser shared test resources in test script editor (88446)

Best Regards,

Bing Dong
Silvia Mesturino selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,132

Question asked: Jun 03 '13, 8:20 a.m.

Question was seen: 3,601 times

Last updated: Jun 04 '13, 2:12 a.m.

Confirmation Cancel Confirm