Copying Test Executions to another Iteration.
Hi,
We're running 4.0 and I've gone through the manual on how to copy an execution to another iteration and its just not showing the option in action menu.
I've got an iteration in the Test Plan Test Schedule and have a list of Test Executions in the Test Plan but even when I select one Test Execution record no option to copy to another iteration appears.
Is there anything else I could be doing wrong?
Thanks,
Dan.
|
One answer
This feature is available in RQM v401. See Copy TER to iteration
Comments
Dan Evans
commented Nov 30 '12, 1:22 p.m.
So this functionality is not available in 4.0 then. Is there an alternative way of doing it? |
Your answer