What day length is used in estimates?

Hi
Using the eclipse client, I create a task for myself and give it an estimate of 2d (for example). I then run a query from the Team Artifacts view and the task is listed in the Work Items view. But the estimate shown in the Work Items view is (incorrectly) 1 day 6 hours. If I open the task, the estimate shows up correctly as 2d. Why is the estimate shown up differently between the two places?

In Team Organization under my user profile in the Work Environment tab, I have set my work time to be 7h 30m for every day, but when I change this, it doesn't change the problem I have with the estimates. My project administrator tells me that the working day has been set to 7 hours for the whole project.

Thanks in advance for your help,
Mark

0 votes



One answer

Permanent link
In Team Organization under my user profile in the Work Environment
tab, I have set my work time to be 7h 30m for every day, but when I
change this, it doesn't change the problem I have with the estimates.
My project administrator tells me that the working day has been set to
7 hours for the whole project.

The Work Items view does not respect the work hours per day setting, but
assumes a 8h work day. I've opened defect 62104
(https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/62104)
to track this.

--
MikeS
Jazz Agile Planning team

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Oct 03 '08, 9:26 a.m.

Question was seen: 4,487 times

Last updated: Oct 03 '08, 9:26 a.m.

Confirmation Cancel Confirm