Why don't all plan items show up on my backlog plan?
![]()
I have a product backlog plan that shows 86 work items, but it should show way more and when I click on the link at the top of the plan that says "86 Open", the Work Items view will show 296 work items. That's correct, I should have 296 items in the backlog plan, but why don't they all show up in the plan?
The plan is for the team that is associated with the root category of the timeline where the backlog is an iteration of. Thanks, Troy |
Accepted answer
![]()
The problem was that the Enhancement type wasn't considered a "plan item". Once I edited the Process Configuration - Project Configuration > Configuration Data > Planning > Work Item Type Categorization and checked the checkbox for Enhancement, then they showed up in my plan.
Still unknown to me was that some Enhancements were showing up - maybe they were stories to begin with?? Also, Enhancement wasn't considered an Execution Item either, because I didn't have that filter checked in my plan. My type (that I created based off another team's project area) had some issues, I guess. Ralph Schoon selected this answer as the correct answer
Comments ![]() FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Troy, there is, based on the the plan type, a default filter that filters away execution items. Instead of making the enhancement request a plan item, you can set the flag "Always load all execution items" in the (advanced) configuration of the plan. |