How to link Test Case with another Test Case in RQM?


yk wu (4611016) | asked Aug 22 '12, 8:47 p.m.
Dear All,

How to link Test Case (TC) with another Test Case in RQM (without using test suite) ?

Reason is that: If I want to build dependency between TCs, for example, I need to run TC for login before TCs for different transactions. And I'd like to make sure that TC for login will be run before  running TCs for different transactions.

Or can you please share any other approach ?

Thanks in advance,

Accepted answer


permanent link
Paul Slauenwhite (8.4k12) | answered Aug 23 '12, 7:00 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
A test suite is the recommended approach.  There are no associations between test cases.