When duplicating test case with requirement traceability to another project, "No" new requirement traceability can be created. Is it working as design ?


yk wu (4611016) | asked Sep 02 '12, 11:54 p.m.

Dear All (RQM Dev Team),

Let's say I have RRC req to RQM test case traceability in Project A. And when I duplicate the RQM Test case to Project B,  "No" new requirement traceability can be created for test case in Project B.

Is this working as design ? Should I raise an enhancement request on this  ?

Thanks in advance,

Accepted answer


permanent link
Paul Slauenwhite (8.4k12) | answered Jan 14 '13, 3:06 p.m.
FORUM MODERATOR / JAZZ DEVELOPER
The forward links should be copied.  There was an issue with copying the backlinks, which was addressed in RQM 4.0.1(see Provide backlink status in traceability view (54955)).  You should be able to manually create forward/back links for the copied test case.
yk wu selected this answer as the correct answer

2 other answers



permanent link
Hao Wan (1.5k35) | answered Sep 03 '12, 2:56 a.m.
JAZZ DEVELOPER
Hi yk,
does the "Project B" associated with the same rm project area as "Project A"?

permanent link
yk wu (4611016) | answered Jan 14 '13, 3:32 a.m.
yes, "Project B" associates with the same rm project area as "Project A".