Upgrade to v4.0. Any proces/reports/template upgrades needed.


Sterling Ferguson-II (1.6k8275268) | asked Aug 10 '12, 1:32 p.m.
 Upgrade to v4.0 is complete.

Was there a need to upgrade the process templates, reports, dashboard, etc? Or are there no new
changes that would require this?

One answer



permanent link
sam detweiler (12.5k6194201) | answered Aug 11 '12, 7:44 p.m.
Yes, at least the email templates are added to the V4 process template.. you must 'upgrade' them..

and I think its ugly..  have to make sure they are all installed on a V3 system, and upgrade that system to get the templates upgraded.

you cannot install an exported V3 template on V4 and have it upgraded.

Comments
Sterling Ferguson-II commented Aug 13 '12, 12:31 p.m.

So how/where do I do this upgrade?