edited Jul 03 '12, 10:35 a.m. by Geoffrey Clemm (30.1k●3●30●35) Hi, We are using RTC / RQM 3.0.1.x and we have linked both RQM & RTC. We do link the Test Cases which we wanted to execute as part of verifying a defect / Use Case in RTC. We have a requirement where we want to know out of 'x' number of defects in an RTC iteration, how many of them have been completed. Or what is the current status of execution of those defcts. for example, A report something like this would be helpful. Planned for -> Iteartion 10 RQM Test Plan -> Test Plan for Iteration-10 Defect# #TERs #TERs_Attempted #TERs_failed #TERs_Passed ......blocked, inconclusive etc ======= ------ --------------- ----------- ----------- 3333 10 10 0 10 4444 25 15 10 0 Can somebody help us here? Regards Prasanna
|
One answer
Hi Prasanna,
The closest report you will find, I think is the "Execution and Defects by Owner" report. The focus of that report (ie the columns of data moving left to right) is from TER Owner to Test Plan to TER Result to Defect but I think the information you are looking for is there. I hope that helps, Mark |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.