It's all about the answers!

Ask a question

How to get a report of work items & TERs linked between RTC & RQM ?


Prasanna Holla (1153) | asked Jul 03 '12, 10:26 a.m.
edited Jul 03 '12, 10:35 a.m. by Geoffrey Clemm (30.1k33035)
Hi, 

We are using RTC / RQM 3.0.1.x and we have linked both RQM & RTC. We do link the Test Cases which we wanted to execute as part of verifying a defect / Use Case in RTC. 

We have a requirement where we want to know out of 'x' number of defects in an RTC iteration, how many of them have been completed. Or what is the current status of execution of those defcts.  

for example, A report something like this would be helpful.

Planned for -> Iteartion 10
RQM Test Plan -> Test Plan for Iteration-10

Defect#    #TERs   #TERs_Attempted  #TERs_failed #TERs_Passed  ......blocked, inconclusive etc
=======   ------            ---------------       -----------               -----------
3333           10                        10                0           10
4444           25                         15               10            0

Can somebody help us here? 

Regards
Prasanna

One answer



permanent link
Mark Victory (26635) | answered Jul 03 '12, 1:44 p.m.
JAZZ DEVELOPER
Hi Prasanna,

The closest report you will find, I think is the "Execution and Defects by Owner" report.
The focus of that report (ie the columns of data moving left to right) is from TER Owner to Test Plan to TER Result to Defect but I think the information you are looking for is there.

I hope that helps,
Mark

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.