Has anyone changed the owner of a Stream that crosses a Project Area boundary?


Susan Hanson (1.6k2201194) | asked Jun 06 '12, 8:06 a.m.
retagged Jun 06 '12, 2:08 p.m. by Evan Hughes (2.4k1318)
I have a stream in Project Area A, owned by Team A.
I need to "move" it to Project Area B, owned by team B.

Reading the InfoCenter, it looks like all I have to do is go to the stream in Project Area A and do a Change Owner, select Team B in Project Area B.

I wanted to be SURE that this will work ... we have source in this stream and I want to be sure I am not going to do anything that will lose anything.  Has anyone done this ? and if so, is this correct??

Susan

One answer



permanent link
Evan Hughes (2.4k1318) | answered Jun 06 '12, 2:08 p.m.
JAZZ DEVELOPER
edited Jun 06 '12, 5:18 p.m.
It will work. 

The only changes that will cause is visibility of the contents of the stream (ie, read access) and which process runs when you deliver, etc. 

EDIT: You can always check your change by duplicating the stream, then changing its owner and seeing what happens. 