Project plan, quick query syntax: variance algorythm?

Hello,

I'm trying to understand how "variance" operator in a plan's quick query works. I've tried to find out any info in help but failed.

My understanding is that it works for the plan that has snapshot of "Planned" type and applies to the tasks that has difference between Planned Start Date and Actual Start Date or Planned End Date and Actual End Date.

Am I right?

-thanks in advance

0 votes



4 answers

Permanent link
Hi Timur,

The Planned Time Variance attribute gives the difference between Planned start and end dates which are stored in a "Planned" type snapshot and the current dates shown in the Gantt chart i.e the Accumulated Time.

Thanks,
Sharoon

Hello,

I'm trying to understand how "variance" operator in a plan's quick query works. I've tried to find out any info in help but failed.

My understanding is that it works for the plan that has snapshot of "Planned" type and applies to the tasks that has difference between Planned Start Date and Actual Start Date or Planned End Date and Actual End Date.

Am I right?

-thanks in advance

0 votes


Permanent link
Hi Sharoon!

Thanks for clarification! When we are talking about current dates do we mean the dates that are stored in Actual Start\End date fields?

-thanks in advance

0 votes


Permanent link
The current dates refer to the dynamic schedule created by the scheduler which is stored in the Accumulated Time attribute and which is represented as a bar in the Gantt chart or Road map.

What is the version of RTC you are using? We do not have an Actual End date attribute but have a Resolved date attribute. The Actual start date attribute is the first instance of the state transition of the work item from a open group to a inprogress group state.

Thanks,
Sharoon

Hi Sharoon!

Thanks for clarification! When we are talking about current dates do we mean the dates that are stored in Actual Start\End date fields?

-thanks in advance

0 votes


Permanent link
Thanks, for clarification Sharoon!

I use 3.0.1.2

-Timur

The current dates refer to the dynamic schedule created by the scheduler which is stored in the Accumulated Time attribute and which is represented as a bar in the Gantt chart or Road map.

What is the version of RTC you are using? We do not have an Actual End date attribute but have a Resolved date attribute. The Actual start date attribute is the first instance of the state transition of the work item from a open group to a inprogress group state.

Thanks,
Sharoon

Hi Sharoon!

Thanks for clarification! When we are talking about current dates do we mean the dates that are stored in Actual Start\End date fields?

-thanks in advance

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Mar 15 '12, 12:16 p.m.

Question was seen: 5,453 times

Last updated: Mar 15 '12, 12:16 p.m.

Confirmation Cancel Confirm