It's all about the answers!

Ask a question

acurracy of progress in plans


Paula White (622) | asked Jan 30 '12, 5:46 p.m.
RTC Progress format

Plans in RtC are showing a super high level of accuracy , 1000's of seconds, with estimate of 40 hours being displayed as 144000000 !

Is there a format setting somewhere that will set this back to display in a more sensible way?

3 answers



permanent link
Brad Veitch (11078) | answered Jan 31 '12, 12:24 a.m.
In the Process Configuration tab, check the
Project Configuration - Configuration Data - Planning - General

Track Progress as: Time Spent or Time Remaining
Is Display estimates in hours checked?

permanent link
Paula White (622) | answered Feb 02 '12, 3:37 a.m.
In the Process Configuration tab, check the
Project Configuration - Configuration Data - Planning - General

Track Progress as: Time Spent or Time Remaining
Is Display estimates in hours checked?



HI Brad thanks, yes I have tried this and this does change the estimate display from hours to days. However the progress is still represented as before, which is still a bit curious.

permanent link
Aradhya K (1.4k44345) | answered Aug 22 '12, 1:46 a.m.
JAZZ DEVELOPER
 Hi

Sorry for the delayed response.
The problem is your case is that you have set the complexity attribute as Estimates or time spent or some attribute whose type is duration.
Estimates are stored as duration(stored internally as milliseconds), that is the reason why the progress bars are showing the progress in milliseconds.
You can set the complexity to an integer type customer attribute or an Enumeration whose IDs are numbers similar to the Story Points enumeration in scrum template.

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.