Curious values for field 'time spent' in a report
We wanted to use a report to get hours done on tasks for all stories in our backlog.
We didn't find a correct field and used f.e. 'time spent'.
We get here very strange values:
23,99916667
1,998611111
20,99916667
13,99972222
-0,001111111 --> especially this story does have as progress value with 9,5h
What is the reason of this values? What do we wrong? Is it true that we have to set '0' explicitly into field 'time remaining' for each task?
I assumed that if I set the task to 'done' then the time will be calculated correct even the field 'time remaining' is empty/initial.
We didn't find a correct field and used f.e. 'time spent'.
We get here very strange values:
23,99916667
1,998611111
20,99916667
13,99972222
-0,001111111 --> especially this story does have as progress value with 9,5h
What is the reason of this values? What do we wrong? Is it true that we have to set '0' explicitly into field 'time remaining' for each task?
I assumed that if I set the task to 'done' then the time will be calculated correct even the field 'time remaining' is empty/initial.
One answer
I have the same problem, I get values like 24.771.600 or 81,108,00.
Is there a answer yet?
Is there a answer yet?
Comments
Hi Sandra, I didn't get an answer. But the stranges values disappear if I set all tasks of a story not only to 'DONE' but also set the field 'Time remaining' = 0.
Kind regards
Hi Anne, thanks for the anwer but we change the template from time remaining to time spent.
So anyone else a idea, where the values coming from?
Greetings Sandra