Build schedule interval vs build duration
Hi,
I'm looking at issues with RQM accurately gathering build records from RTC. What is happening is that build records are showing up in RTC with NaN for Completion time (this detail is planned to be fixed in v4 according to findings). However, I would like to inquire the effect of having a schedule interval shorter than the consistent build duration (10% longer than the interval) on the proper functioning of the Jazz Build engine and the associated records received by RQM. The build is configured for 30 minute intervals, with "Build only if changes" is checked but the build duration is 35-50 minute range. Thanks Kevin |
Be the first one to answer this question!