We are trying to use the estimate field but it is capped at 52 weeks. Is there any way to remove this limitation and allow us to have estimates larger than 1 year?

0 votes



2 answers

Permanent link
I'd suggest breaking a task that will be longer than a year into sub-tasks.

Cheers,
Geoff

On 1/10/2012 5:23 PM, lhammond wrote:
We are trying to use the estimate field but it is capped at 52 weeks.
Is there any way to remove this limitation and allow us to have
estimates larger than 1 year?

0 votes

Comments

Thanks for your suggestion, but is it possible to change to the max value for this field? or how to remove this limitation on the estimate field?


Permanent link

 I just noticed this limitation and was wondering if it has been fixed in recent releases (6.x.) ?

Thanks in advance for any pointer.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jan 10 '12, 5:19 p.m.

Question was seen: 3,836 times

Last updated: Jan 17 '18, 1:12 p.m.

Confirmation Cancel Confirm