Estimate field capped at 52 weeks
We are trying to use the estimate field but it is capped at 52 weeks. Is there any way to remove this limitation and allow us to have estimates larger than 1 year?
|
2 answers
Geoffrey Clemm (30.1k●3●30●35)
| answered Jan 11 '12, 12:08 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
I'd suggest breaking a task that will be longer than a year into sub-tasks.
Cheers, Geoff On 1/10/2012 5:23 PM, lhammond wrote: We are trying to use the estimate field but it is capped at 52 weeks. Comments
Prasannakumar Copparam
commented Nov 05 '12, 12:55 a.m.
Thanks for your suggestion, but is it possible to change to the max value for this field? or how to remove this limitation on the estimate field?
|
I just noticed this limitation and was wondering if it has been fixed in recent releases (6.x.) ?
Thanks in advance for any pointer.
|