Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

How does the "Progress" is calculated in "Business need" work item?

I have a "Business need", inshort BN, which is having one "Task" as childern
  1. When the Task has no effort, the "Progress" in BN shows 75% and bar is filled with green
  2. When the Task has estimate, say 5h and 0h Time spent, the "Progress" in  BN shows 75% 0/5h and bar is not filled 
  3. When the time spent is 3h in Task, the "Progress" in BN shows 3/5h, 75% and bar filled more than 50%

my questions are the following w.r.to "Business Need" 
  1. What is the logic behind calculating the % ?
  2. What is the logic behind calculating the hours ?
  3. What is the logic behind filling the progress bar?
  4. Where is the value calculation happening in the Project Area?

0 votes



One answer

Permanent link
In general, completely independent of the type of the work item, there are two categorizations for work items. Execution items and plan items. Execution items (task, defect), are not marked as plan items and track effort done to achieve them. Plan items usually roughly estimate the complexity of doing them and aggregate effort by child execution items.

https://jazz.net/library/article/586 explains how the bars work based on these concepts.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,023

Question asked: Mar 18 '16, 12:06 p.m.

Question was seen: 1,729 times

Last updated: Mar 21 '16, 4:43 a.m.

Confirmation Cancel Confirm