How does the "Progress" is calculated in "Business need" work item?
I have a "Business need", inshort BN, which is having one "Task" as childern
my questions are the following w.r.to "Business Need"
|
One answer
Ralph Schoon (63.1k●3●36●45)
| answered Mar 21 '16, 4:43 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
In general, completely independent of the type of the work item, there are two categorizations for work items. Execution items and plan items. Execution items (task, defect), are not marked as plan items and track effort done to achieve them. Plan items usually roughly estimate the complexity of doing them and aggregate effort by child execution items.
https://jazz.net/library/article/586 explains how the bars work based on these concepts. |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.