Tracking Committed Points?

Hi,

My Agile teams using RTC want to track the number of points they commit to each sprint, and the number of points they get done each Sprint.

Currently in our RTC when you move a Story out of the current Sprint, you lose track of the fact that the team committed to those points even though they were not completed.

Is there anyway to automatically record the number of points that were originally committed to, even when some stories are later moved out of the Sprint?

Thank you,
Evan

0 votes



2 answers

Permanent link
Evan,

I think plan snapshots should help. However, I tried to use them, but they didn't work well in RTC 3.0 ifix1.

You can create a plan snapshot and then create regular snapshots to compare to the first one.

Hope this helps.

Juan

0 votes


Permanent link
Thank you Juan. I did eventually find that feature, which seems to meet the requirement. Thank you!

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Nov 07 '11, 1:42 p.m.

Question was seen: 4,635 times

Last updated: Nov 07 '11, 1:42 p.m.

Confirmation Cancel Confirm