Best Practice: Project Areas Vs Team Areas
Hi all
We have an account adopting CLM with Rational Team Concert 3.0.1 as a start. This account will have around 60+ project teams with 700+ users. What would be the best practice on setting up project areas and team areas. Which of the above two approaches is advisable? Do we have any documents/articles that talk of best practices to be followed for project area setup. Thanks in advance!! Thanks & Regards Vinay |
One answer
Geoffrey Clemm (30.1k●3●30●35)
| answered Aug 22 '11, 1:53 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER edited Aug 20 '13, 6:59 p.m.
I recommend thinking of a project area as "a place where projects live"
(not as "a place where a single project lives"). Probably a "process area" would have been a better name, since the main point of a project area is to define a general process shared by all of the teams working in that project area (but where a team can customize various aspects of that process to more closely match their needs). So I'd recommend Approach A, unless there are good reasons to have multiple project areas, such as that some projects have a significantly different process, which cannot be modeled in RTC just as a customized variant of a shared process. Cheers, Geoff Comments 1
Thanks Geoff for your reply. My concerns on using multiple Team Areas over Project Areas were as below:
1
Geoffrey Clemm
commented Aug 23 '11, 2:49 p.m.
| edited Aug 21 '13, 10:57 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
A terminological note ... the process defined in a project area is called the "Process Configuration". A "Process Template" is something else (it is an "exported" form of the process configuration, that can be used to initialize the process configuration of a new project area).
1
Come back to this question. I am using approach A right now, e.g. all our Curam based application are in one project area. They share the same formal project management process.
1
Geoffrey Clemm
commented Dec 16 '11, 5:53 p.m.
| edited Aug 20 '13, 7:07 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
In your case, the only real meaning for the project timeline is that it is the timeline that a new top level team area is initialized to refer to.
1
Susan Hanson
commented Aug 20 '13, 9:26 p.m.
We've been having this conversation for a set of projects. There are pros and cons to each ...We find doing process configuration at a team to be error prone. As well, my understanding is that the work item definitions/workflows are at a project area. If one team wants to have their own custom work item or add custom attributes, they go to ALL teams in the project area, even if not used.
Ratheesh Madathil
commented Aug 21 '13, 12:18 p.m.
Hello Geoff, We have almost the same context like mentioned in the question above. We are trying to set this up for a product division of about 500 people. The basics about project area and team are was read through the blogs already. Project normally has planning people (project coordinators with OEM) and implimention teams. Implimention team consists of people from software, hardware, applciation etc...but situated world wide. Each of this above team requires different kind of information, there for different fields in the workitem. We currently think about having the "Plan" area for each OEM as seperate "Project area" and "implimentation" area for each discipline mentioned above also as different project areas. Under these of course we need team area for different functions. But then definitely need "cross-project" plan so that the planning guys can track the progress from implimentions. What is your opinion on this? Is that can be still optimised to one "project area"?.
Geoffrey Clemm
commented Aug 21 '13, 11:54 p.m.
| edited Aug 21 '13, 11:56 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Ratheesh: Yes, I would strongly recommend trying hard to use a single project area for both the planners and the implementers of a project. Information flow between the planners and the implementers should be the highest priority.
Geoffrey Clemm
commented Aug 23 '13, 1:42 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Note: I have moved Karsten's comment to be a separate question: https://jazz.net/forum/questions/124321
showing 5 of 8
show 3 more comments
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.