Hello,

We use the Scrum template to manage our project. We created 2 Teamareas and 4 other sprints next to the predefined from project creation.
The BurnDown chart worked as expected for the first and for the second sprint. But now (we are in 3rd sprint) it says "No data available." for example in the Plan Details.

When I look at the burndown chart on the dashboard it looks very different from the sprints before because the expected complete line starts in the left bottom corner and ends in right top. In the Sprints before it was from left top to right bottom. Although in the burndown query i am not able to select another iteration than the current or the first or second sprint. The other 4 Sprints we created are not visible. I checked the permission, but I do not know which could influnce this topic, that's why I gave myself as role teammember all possible permissions on project and team level, but that did not work.

When i go to the report section an run the burndown chart it says "No work items with estimates specified were found." I run the data collection jobs and checked the estimated value (all tasks have one).

And now I do not know what else I can do. Did I miss something or is this a bug?

regards
Maria

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jul 22 '11, 12:23 p.m.

Question was seen: 3,316 times

Last updated: Jul 22 '11, 12:23 p.m.

Confirmation Cancel Confirm