It's all about the answers!

Ask a question

How to define a new work item type in RTC?


Kamal Suruguchi (15112114) | asked May 11 '11, 6:02 a.m.
In RTC, how can I define a new Work Item Type (other than the existing Defect, Task, Story, Epic, etc.)? Is it possible by some configuration in the UI or is it only through some RTC extension?

2 answers



permanent link
Jose Miguel Ordax Cassa (2.4k4126100) | answered May 12 '11, 2:29 a.m.
On 5/11/2011 12:08 PM, kamalsur wrote:
In RTC, how can I define a new Work Item Type (other than the existing
Defect, Task, Story, Epic, etc.)? Is it possible by some configuration
in the UI or is it only through some RTC extension?

You can do that in Project Area configuration editors.
Check Jazz.net articles. There are couple about how to do that step by step.

permanent link
Kamal Suruguchi (15112114) | answered May 16 '11, 3:00 a.m.
On 5/11/2011 12:08 PM, kamalsur wrote:
In RTC, how can I define a new Work Item Type (other than the existing
Defect, Task, Story, Epic, etc.)? Is it possible by some configuration
in the UI or is it only through some RTC extension?

You can do that in Project Area configuration editors.
Check Jazz.net articles. There are couple about how to do that step by step.

Thanks!

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.