Clearcase baselines import in RTC 2.0.0.2
We are trying to import files from Clearcase UCM into RTC with Clearcase Importer.
We'd like to import Clearcase baselines in RTC baselines but actually, they are imported in RTC Change sets. Is there a way to import Clearcase UCM baselines into RTC baselines ? |
4 answers
Geoffrey Clemm (30.1k●3●30●35)
| answered Mar 03 '11, 12:53 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
You can get this enhancement by upgrading to RTC-3.0.
Cheers, Geoff On 3/2/2011 5:53 AM, aureliencoueron wrote: We are trying to import files from Clearcase UCM into RTC with |
Geoffrey Clemm (30.1k●3●30●35)
| answered Mar 03 '11, 11:08 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Yes, I'm sure, but you have to know where to find them (:-).
They aren't in the sync stream (that would disrupt the change flow). So to find those baselines, right click on the component in the Team Artifact Navigator (you'll find the component under the Source Control node in the project area that owns the component), and select "Show Baselines". Or right click on the component in some stream/workspace, and select "Replace_with -> Baseline..." (remember to select "Clear_Filter"). Cheers, Geoff On 3/3/2011 5:53 AM, aureliencoueron wrote: Thanks for your reply. |
Thanks for the tip to locate the baselines. It was difficult to find :-)
Why the imported baselines are not displayed in the sync stream and are hidden? Why showing these would disrupt the changeflow? Many thanks, Ana On 04/03/2011 4:55, Geoffrey Clemm wrote: Yes, I'm sure, but you have to know where to find them (:-). |
Geoffrey Clemm (30.1k●3●30●35)
| answered May 03 '11, 11:25 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
The imported baselines are not delivered by the synchronizer to the sync
stream because those imported baselines may not be compatible with baselines that the user has created in the sync stream. This would mean that if the synchronizer delivered those baselines to the sync stream, the deliver would remove the incompatible user-created baselines from the sync stream. This actually was what we did in RTC-1.0, but removed this behavior in RTC-2.0 because of (understandable) user objections. Cheers, Geoff On 5/3/2011 3:52 PM, Ana Lopez wrote: Thanks for the tip to locate the baselines. It was difficult to find :-) |
Your answer