Hi

I wonder how I can see the total time available in a sprint plan, based on the availability of the team members and the estimated tasks planned for the sprint.

Ideally, I would like to see this in the top right corner together with the progress information. I can see there how many hours are in the sprint, but not how many are totally available.

Seeing this number would make it easy to know when the sprint plan is getting "full", without having to calculate the available hours by hand, or first assign all tasks to the team members in order to see in their Load how they are allocated. Does anybody else have this problem?

I'm using 2.0, maybe it is fixed in 3.0?

Cheers
/Gran

0 votes

Comments

I see it is an old post, but did you get the answer? I am wondering the same thing.



One answer

Permanent link
I can't remember that I ever got an answer to this, no. But I have not used RTC for almost a year now, so my memory might fail me. We went up to 3.0 though, and I don't think it was available there either.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jan 31 '11, 5:30 a.m.

Question was seen: 4,590 times

Last updated: Aug 03 '12, 11:01 a.m.

Confirmation Cancel Confirm