Questions on Formal Project Management Template

.. Running RTC 3.0 on Windows 7 64-bit:
1. Though only Change Requests and Business Needs are configured as Top
Level Plan items and "Include all items" is unchecked the Work breakdown
and schedule view for a Release plan still shows Tasks planned for the
iteration.
2. With the iteration dates set to a four month period, adding even a
single task without an estimate shows the task as critical (red) in the
Gantt view. This doesn't seem right?
3. How exactly does the "Zoom to selection" work?

Thanks

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jan 21 '11, 8:23 a.m.

Question was seen: 2,817 times

Last updated: Jan 21 '11, 8:23 a.m.

Confirmation Cancel Confirm