Questions on Formal Project Management Template
.. Running RTC 3.0 on Windows 7 64-bit:
1. Though only Change Requests and Business Needs are configured as Top
Level Plan items and "Include all items" is unchecked the Work breakdown
and schedule view for a Release plan still shows Tasks planned for the
iteration.
2. With the iteration dates set to a four month period, adding even a
single task without an estimate shows the task as critical (red) in the
Gantt view. This doesn't seem right?
3. How exactly does the "Zoom to selection" work?
Thanks
1. Though only Change Requests and Business Needs are configured as Top
Level Plan items and "Include all items" is unchecked the Work breakdown
and schedule view for a Release plan still shows Tasks planned for the
iteration.
2. With the iteration dates set to a four month period, adding even a
single task without an estimate shows the task as critical (red) in the
Gantt view. This doesn't seem right?
3. How exactly does the "Zoom to selection" work?
Thanks