Work item - make the Due Date to be required.


xudong xuan (2134) | asked Dec 06 '10, 8:02 a.m.
I want to know in RTC, is it possible to make the Due Date to be required when use changes the status to 'in process'? and how?

2 answers



permanent link
Ralph Schoon (63.1k33645) | answered Dec 06 '10, 8:56 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi,

this is possible in the Project's Process Configuration editor by adding a "required attributes" precondition. There you can select the work item types and transitions when you add the precondition to the roles in the Team configuration.

You might also want to to read this article http://jazz.net/library/article/292 on how the behavior lookup works.

Ralph

I want to know in RTC, is it possible to make the Due Date to be required when use changes the status to 'in process'? and how?

permanent link
xudong xuan (2134) | answered Dec 06 '10, 9:06 a.m.
Hi,

this is possible in the Project's Process Configuration editor by adding a "required attributes" precondition. There you can select the work item types and transitions when you add the precondition to the roles in the Team configuration.

You might also want to to read this article http://jazz.net/library/article/292 on how the behavior lookup works.

Ralph

I want to know in RTC, is it possible to make the Due Date to be required when use changes the status to 'in process'? and how?


Yes, it works, thanks very much!