I want to know in RTC, is it possible to make the Due Date to be required when use changes the status to 'in process'? and how?

0 votes



2 answers

Permanent link
Hi,

this is possible in the Project's Process Configuration editor by adding a "required attributes" precondition. There you can select the work item types and transitions when you add the precondition to the roles in the Team configuration.

You might also want to to read this article http://jazz.net/library/article/292 on how the behavior lookup works.

Ralph

I want to know in RTC, is it possible to make the Due Date to be required when use changes the status to 'in process'? and how?

0 votes


Permanent link
Hi,

this is possible in the Project's Process Configuration editor by adding a "required attributes" precondition. There you can select the work item types and transitions when you add the precondition to the roles in the Team configuration.

You might also want to to read this article http://jazz.net/library/article/292 on how the behavior lookup works.

Ralph

I want to know in RTC, is it possible to make the Due Date to be required when use changes the status to 'in process'? and how?


Yes, it works, thanks very much!

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Dec 06 '10, 8:02 a.m.

Question was seen: 4,257 times

Last updated: Dec 06 '10, 8:02 a.m.

Confirmation Cancel Confirm