Can't create a plan?
3 answers
Hi Scott,
I suspect that you can only select iterations of a timeline that the team the plan is owned by is working against. Please chack the Category tab of the process configuration.
Another possible cause would be that the grayed out iterations have not been marked as "A release is scheduled for this iteration". Those iterations can't be used for planning because they are not meant to deliver anything.
Ralph
I suspect that you can only select iterations of a timeline that the team the plan is owned by is working against. Please chack the Category tab of the process configuration.
Another possible cause would be that the grayed out iterations have not been marked as "A release is scheduled for this iteration". Those iterations can't be used for planning because they are not meant to deliver anything.
Ralph
For some reason when I create a plan I am able to select some iterations but not others; some the OK button is grayed out.
Why are some not selectable?
That was it. Since it allows me to select those, just not hit "OK" it should tell me in the dialog box why that selection is unacceptable.
Just a suggestion...
Thanks!
Just a suggestion...
Thanks!
Hi Scott,
I suspect that you can only select iterations of a timeline that the team the plan is owned by is working against. Please chack the Category tab of the process configuration.
Another possible cause would be that the grayed out iterations have not been marked as "A release is scheduled for this iteration". Those iterations can't be used for planning because they are not meant to deliver anything.
Ralph
For some reason when I create a plan I am able to select some iterations but not others; some the OK button is grayed out.
Why are some not selectable?