Migrate project area across RTC repositories
We have request to migrate one project area from one RTC repository to another.
We are told that at 2.0.0.2 this is not doable.
What really needs to be migrated is the work items and SCM components and streams.
I've triedwork items migration before. But never did the SCM component and stream migration.
Our customer wants to keep the links between the SCM changesets and work items.
Has anyone tried this before?
We are told that at 2.0.0.2 this is not doable.
What really needs to be migrated is the work items and SCM components and streams.
I've triedwork items migration before. But never did the SCM component and stream migration.
Our customer wants to keep the links between the SCM changesets and work items.
Has anyone tried this before?
One answer
You cannot migrate individual components or streams in 2.0.0.2, but you
will be able to deliver change sets across repositories in 3.0, which
effectively lets you migrate (at least key parts of) components and streams.
Cheers,
Geoff
On 10/21/2010 8:38 AM, ghu wrote:
will be able to deliver change sets across repositories in 3.0, which
effectively lets you migrate (at least key parts of) components and streams.
Cheers,
Geoff
On 10/21/2010 8:38 AM, ghu wrote:
We have request to migrate one project area from one RTC repository to
another.
We are told that at 2.0.0.2 this is not doable.
What really needs to be migrated is the work items and SCM components
and streams.
I've triedwork items migration before. But never did the SCM component
and stream migration.
Our customer wants to keep the links between the SCM changesets and
work items.
Has anyone tried this before?