[3.0 RC0] Time Tracking reports
Hi,
I'm using Formal Project Management Template and Time Tracking information related to Task.
I'm wondering if there are reports that extract this information.
An interesting one could be a detailed report of master-details work items (e.g. from a Plan Item WI, see all related Tasks WI - childrens - with Time Tracking for each Task and a total at Plan Item level).
Thanks
Paolo
I'm using Formal Project Management Template and Time Tracking information related to Task.
I'm wondering if there are reports that extract this information.
An interesting one could be a detailed report of master-details work items (e.g. from a Plan Item WI, see all related Tasks WI - childrens - with Time Tracking for each Task and a total at Plan Item level).
Thanks
Paolo
3 answers
Hi,
I'm using Formal Project Management Template and Time Tracking information related to Task.
I'm wondering if there are reports that extract this information.
An interesting one could be a detailed report of master-details work items (e.g. from a Plan Item WI, see all related Tasks WI - childrens - with Time Tracking for each Task and a total at Plan Item level).
Thanks
Paolo
I was curious about this too and got this response from someone on the development team:
Currently we've two reports
i) Timesheet Details -- Timesheet details for selected group of users (with task name) for a given period of time ( year, quarter, month, week)
ii) Timesheet Summary -- Total time spent for selected group of users for a given period of time (year, quarter, month, week).
Master details WI scenario is not there, as users are the prime import for timesheets.
Thanks Kevin.
Do you know where I can find these reports? Under Shared Reports there aren't reports related to Timesheet data.
Tks Paolo
I was curious about this too and got this response from someone on the development team:
Do you know where I can find these reports? Under Shared Reports there aren't reports related to Timesheet data.
Tks Paolo
Hi,
I'm using Formal Project Management Template and Time Tracking information related to Task.
I'm wondering if there are reports that extract this information.
An interesting one could be a detailed report of master-details work items (e.g. from a Plan Item WI, see all related Tasks WI - childrens - with Time Tracking for each Task and a total at Plan Item level).
Thanks
Paolo
I was curious about this too and got this response from someone on the development team:
Currently we've two reports
i) Timesheet Details -- Timesheet details for selected group of users (with task name) for a given period of time ( year, quarter, month, week)
ii) Timesheet Summary -- Total time spent for selected group of users for a given period of time (year, quarter, month, week).
Master details WI scenario is not there, as users are the prime import for timesheets.
I have not been through this exercise myself but I did get this comment from the development team:
Along with this link for more detailed guidance:
https://jazz.net/wiki/bin/view/Main/CALMReportingTesting
I hope this helps.
I was curious about this too and got this response from someone on the development team:
All the common planing reports (timesheet reports included) come as Cognos reports.
The Rational Reporting for Developer Intelligence ( the optional reporting component) needs to be installed and configured with RTC first.
These reports are cognos reports and can be viewable only with RR (Rational REporting component).
After installing this optional component, there are couple of archives that needs to be imported.
After the reports are there in RR, we need to include those reports into RTC reports tab (separate instructions are there to do it).
Along with this link for more detailed guidance:
https://jazz.net/wiki/bin/view/Main/CALMReportingTesting
I hope this helps.
Thanks Kevin.
Do you know where I can find these reports? Under Shared Reports there aren't reports related to Timesheet data.
Tks Paolo
Hi,
I'm using Formal Project Management Template and Time Tracking information related to Task.
I'm wondering if there are reports that extract this information.
An interesting one could be a detailed report of master-details work items (e.g. from a Plan Item WI, see all related Tasks WI - childrens - with Time Tracking for each Task and a total at Plan Item level).
Thanks
Paolo
I was curious about this too and got this response from someone on the development team:
Currently we've two reports
i) Timesheet Details -- Timesheet details for selected group of users (with task name) for a given period of time ( year, quarter, month, week)
ii) Timesheet Summary -- Total time spent for selected group of users for a given period of time (year, quarter, month, week).
Master details WI scenario is not there, as users are the prime import for timesheets.