Export to .CVS "Planned fot" attribute presentatio
Hi,
I'm using the Eclipse client (2.0.0.2) I export work items (from Query) using the export work items option to CSV (excel) format. I add the "Planned for" column. The column in excel shows the full path of the iteration (e.g. "/Current Development/Leo/7.5.2.0/7.5.2.0.p2") In case of export to HTML I get the display name, as I would expect. ("7.5.2 P1") and not the ID with full path. I cannot check, but I think it wasn't so in older versions of RTC. I see one benefit, when importing back to RTC, the correct iteration will be set. but for getting information for presentation it's bad. |
One answer
Yes this changed in 2.0.0.2 for the purpose of being able to properly
import these values back into RTC. Otherwise there is no way of guaranteeing that the right iteration is set on import. |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.