Export to .CVS "Planned fot" attribute presentatio


Moti Wertheimer (18913628) | asked Feb 21 '10, 10:20 a.m.
JAZZ DEVELOPER
Hi,

I'm using the Eclipse client (2.0.0.2)
I export work items (from Query) using the export work items option to CSV (excel) format.
I add the "Planned for" column.
The column in excel shows the full path of the iteration (e.g. "/Current Development/Leo/7.5.2.0/7.5.2.0.p2")
In case of export to HTML I get the display name, as I would expect. ("7.5.2 P1") and not the ID with full path.

I cannot check, but I think it wasn't so in older versions of RTC.

I see one benefit, when importing back to RTC, the correct iteration will be set. but for getting information for presentation it's bad.

One answer



permanent link
Work Item & UI Commons Team (1.3k1) | answered Feb 21 '10, 11:38 a.m.
Yes this changed in 2.0.0.2 for the purpose of being able to properly
import these values back into RTC. Otherwise there is no way of
guaranteeing that the right iteration is set on import.