How do I Change default chart type for a plan type?


Kim Soederhamn (1.5k34348) | asked Jun 10 '10, 5:55 a.m.
Hey All,

The default chart on an iteration plan is a burndown chart showing the current sprint and the hours.

For a release plan the default chart is ALSO a burndown chart but it would be much more handy if it was a release burndown chart showing remaining function points.

How can I change this default type?

Accepted answer


permanent link
Michael Dexter (9221114) | answered Sep 14 '12, 8:42 a.m.
 SOLVED!

In your project, navigate to (Reports-Report Templates) Right click the report you want to be the default on the Charts tab and select "Set as Default Plan Chart"
Kim Soederhamn selected this answer as the correct answer

3 other answers



permanent link
Linda Gricius (6812122) | answered Mar 27 '12, 1:57 p.m.
Did you ever get an answer to this question?

permanent link
Kim Soederhamn (1.5k34348) | answered Mar 28 '12, 3:35 a.m.
Did you ever get an answer to this question?


Hi Linda,

We created a work item for it instead - I think it may be comming later - perhaps in v 4.0 but dont remember the work item number - sorry

permanent link
Geoffrey Clemm (30.1k33035) | answered Mar 28 '12, 6:57 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
The closest I found was work item 109427 (which requested this functionality in a comment). I added the text of that comment into the Summary and Description, so this would be a reasonably work item to add a comment indicating your interest/support in this enhancement.

Cheers,
Geoff

Did you ever get an answer to this question?


Hi Linda,

We created a work item for it instead - I think it may be comming later - perhaps in v 4.0 but dont remember the work item number - sorry