How do I assign a particular work item to the entire team
2 answers

A task is assigned to a team by setting its Filed Against field to a
category that is assigned to that team. That makes it show up in the
plans for that team. Or were there some other semantics you had in mind
by "assign"?
Cheers,
Geoff
On 5/21/2010 3:52 PM, shikhasi wrote:
category that is assigned to that team. That makes it show up in the
plans for that team. Or were there some other semantics you had in mind
by "assign"?
Cheers,
Geoff
On 5/21/2010 3:52 PM, shikhasi wrote:
I need to assign a single task to the entire team in my project
area.Hoe do i do it?

A task is assigned to a team by setting its Filed Against field to a
category that is assigned to that team. That makes it show up in the
plans for that team. Or were there some other semantics you had in mind
by "assign"?
Cheers,
Geoff
On 5/21/2010 3:52 PM, shikhasi wrote:
I need to assign a single task to the entire team in my project
area.Hoe do i do it?
Thanks for the help...