"Blocks" and "Depends On"


James Labrie (18123818) | asked Apr 06 '10, 4:46 a.m.
Hi,

I'm using RTC 2.0.0.2.
I have a question about "Blocks" and "Depends On".

In "Links" field of work item, "Blocks" or "Depends On" can be specified.
I have now following work items.

Task1 blocks Task2.
Task2 Depends On Task1.

How does they affect each other?
As far as I have checked, if Task1 is completed, the link in Task2 becomes strikeout text.
If Task2 is completed, the link in Task1 likewise becomes strikeout text .

Is that all effect between "Blocks" and "Depends On"?
Is there another effect besides the appearance?

8 answers



permanent link
Geoffrey Clemm (30.1k33035) | answered Apr 06 '10, 8:47 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi James,

No, there is currently no semantics attached to those links, beyond the
visual that you describe. The Rational Project Conductor project
<http> is working on
adding the semantics to those links.

Cheers,
Geoff

JamesLa wrote:
Hi,

I'm using RTC 2.0.0.2.
I have a question about "Blocks" and "Depends
On".

In "Links" field of work item, "Blocks" or
"Depends On" can be specified.
I have now following work items.

Task1 blocks Task2.
Task2 Depends On Task1.

How does they affect each other?
As far as I have checked, if Task1 is completed, the link in Task2
becomes strikeout text.
If Task2 is completed, the link in Task1 likewise becomes strikeout
text .

Is that all effect between "Blocks" and "Depends
On"?
Is there another effect besides the appearance?

permanent link
Ralph Schoon (63.1k33646) | answered Apr 06 '10, 8:54 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi,

I see not operational behavior that could be configured out of the box.
In general the Blocks relationship is used for dashboards and queries e.g. to display blocking defects. It adds semantic to a dependency.

It would be possible to create operational behavior based on that semantic however. E.g. one could develop a process extension that would for example prohibit resolving a work item while it is still blocked by an unresolved work item.

Ralph

Hi,

I'm using RTC 2.0.0.2.
I have a question about "Blocks" and "Depends On".

In "Links" field of work item, "Blocks" or "Depends On" can be specified.
I have now following work items.

Task1 blocks Task2.
Task2 Depends On Task1.

How does they affect each other?
As far as I have checked, if Task1 is completed, the link in Task2 becomes strikeout text.
If Task2 is completed, the link in Task1 likewise becomes strikeout text .

Is that all effect between "Blocks" and "Depends On"?
Is there another effect besides the appearance?

permanent link
James Labrie (18123818) | answered Apr 09 '10, 12:49 a.m.
Hi James,

No, there is currently no semantics attached to those links, beyond the
visual that you describe. The Rational Project Conductor project
<http> is working on
adding the semantics to those links.

Cheers,
Geoff


Hi Geoff,

Thank you for your reply.
I have a question about your answer.

What is "The Rational Project Conductor project <http>"?
Sorry, I don't know Rational Project Conductor well.

Regards
James

permanent link
James Labrie (18123818) | answered Apr 09 '10, 12:52 a.m.
Hi,

I see not operational behavior that could be configured out of the box.
In general the Blocks relationship is used for dashboards and queries e.g. to display blocking defects. It adds semantic to a dependency.

It would be possible to create operational behavior based on that semantic however. E.g. one could develop a process extension that would for example prohibit resolving a work item while it is still blocked by an unresolved work item.

Ralph


Hi Ralph

Thank you for your reply.

Regards
James

permanent link
Ralph Schoon (63.1k33646) | answered Apr 09 '10, 1:43 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi James,

the Rational Project Conductor is a Jazz based multi project planning tool. You can find more Information here http://jazz.net/projects/rational-project-conductor/

Ralph

Hi James,

No, there is currently no semantics attached to those links, beyond the
visual that you describe. The Rational Project Conductor project
<http> is working on
adding the semantics to those links.

Cheers,
Geoff


Hi Geoff,

Thank you for your reply.
I have a question about your answer.

What is "The Rational Project Conductor project <http>"?
Sorry, I don't know Rational Project Conductor well.

Regards
James

permanent link
James Labrie (18123818) | answered Apr 13 '10, 5:09 a.m.
Hi James,

the Rational Project Conductor is a Jazz based multi project planning tool. You can find more Information here http://jazz.net/projects/rational-project-conductor/

Ralph


Hi Ralph

Thank you for the information.

I went through the link but I could not find the information I want.
Do you know what semantics will be added to the link "Blocks" and "Depends On"?

If yes, could you please let me know?

Thanks
James

permanent link
Ralph Schoon (63.1k33646) | answered Apr 13 '10, 7:42 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi James,

I don't really have a lot more information available than you have.
I don't know what the Project Conductor or the Team Concert team is planning with this dependency.

Sorry,

Ralph

permanent link
James Labrie (18123818) | answered Apr 15 '10, 8:25 a.m.
Hi James,

I don't really have a lot more information available than you have.
I don't know what the Project Conductor or the Team Concert team is planning with this dependency.

Sorry,

Ralph


Hi Ralph

No problem. Please don't be sorry.
Thank you for your cooperation.

Regards
James