"Blocks" and "Depends On"
Hi,
I'm using RTC 2.0.0.2. I have a question about "Blocks" and "Depends On". In "Links" field of work item, "Blocks" or "Depends On" can be specified. I have now following work items. Task1 blocks Task2. Task2 Depends On Task1. How does they affect each other? As far as I have checked, if Task1 is completed, the link in Task2 becomes strikeout text. If Task2 is completed, the link in Task1 likewise becomes strikeout text . Is that all effect between "Blocks" and "Depends On"? Is there another effect besides the appearance? |
8 answers
Geoffrey Clemm (30.1k●3●30●35)
| answered Apr 06 '10, 8:47 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi James,
No, there is currently no semantics attached to those links, beyond the visual that you describe. The Rational Project Conductor project <http> is working on adding the semantics to those links. Cheers, Geoff JamesLa wrote: Hi, |
Ralph Schoon (63.3k●3●36●46)
| answered Apr 06 '10, 8:54 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi,
I see not operational behavior that could be configured out of the box. In general the Blocks relationship is used for dashboards and queries e.g. to display blocking defects. It adds semantic to a dependency. It would be possible to create operational behavior based on that semantic however. E.g. one could develop a process extension that would for example prohibit resolving a work item while it is still blocked by an unresolved work item. Ralph Hi, |
Hi James, Hi Geoff, Thank you for your reply. I have a question about your answer. What is "The Rational Project Conductor project <http>"? Sorry, I don't know Rational Project Conductor well. Regards James |
Hi, Hi Ralph Thank you for your reply. Regards James |
Ralph Schoon (63.3k●3●36●46)
| answered Apr 09 '10, 1:43 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi James,
the Rational Project Conductor is a Jazz based multi project planning tool. You can find more Information here http://jazz.net/projects/rational-project-conductor/ Ralph Hi James, Hi Geoff, Thank you for your reply. I have a question about your answer. What is "The Rational Project Conductor project <http>"? Sorry, I don't know Rational Project Conductor well. Regards James |
Hi James, Hi Ralph Thank you for the information. I went through the link but I could not find the information I want. Do you know what semantics will be added to the link "Blocks" and "Depends On"? If yes, could you please let me know? Thanks James |
Ralph Schoon (63.3k●3●36●46)
| answered Apr 13 '10, 7:42 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi James,
I don't really have a lot more information available than you have. I don't know what the Project Conductor or the Team Concert team is planning with this dependency. Sorry, Ralph |
Hi James, Hi Ralph No problem. Please don't be sorry. Thank you for your cooperation. Regards James |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.