In All Plans I see the following: Sprint 1 Progress 46.75/59.25 Sprint 2 Progress 77.5/82 Sprint 3 Progress 67.5/153.5 Does it mean that the team spent 46.75 h out of the 59.25 they should on the project for sprint 1? Does it mean that 82 h were planned to be spent on the project by the team for sprint 2? Does the time show in sprint 2 contain the time of sprint 1? So the time spent on sprint 2 would be 82-59.25? Thanks Chris |
4 answers
![]()
Ralph Schoon (63.3k●3●36●46)
| answered Mar 29 '10, 2:41 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi,
please see http://jazz.net/library/article/202 More about RTC can be found here: http://jazz.net/projects/rational-team-concert/learnmore/ Ralph Hi, |
![]()
Thanks for the very helpful links.
Christelle Hi, Hi, |
![]()
Hi,
Is there a good link explaining how to submit bugs in RTC? I found http://jazz.net/library/article/42 but was wondering if there is something more. Dr. Scharff |
![]()
Ralph Schoon (63.3k●3●36●46)
| answered Apr 07 '10, 2:06 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi Christelle,
please next time open another topic. I am not sure why this time it was added to the old thread. Do you mean submitting bugs against RTC or how to create work items in RTC? Defect/Bug is just a work item type in RTC and creating work items is possible in RTC at almost every place you'd want to do it. http://jazz.net/projects/rational-team-concert/learnmore/ should cover that as well. Hi, |