Can't edit current iteration plan
One answer
You might have configured the permissions (in the process specification of your project area) for specific iterations. You could instead configure these under <team-configuration>, which will be used for all iterations.
Regards,
Christof
amcohen.us.ibm.com wrote:
Regards,
Christof
amcohen.us.ibm.com wrote:
I noticed that if I set an iteration as current in the Project Area
Editor. I can't edit the Iteration Plans in that iteration anymore. I
get an error stating that I do not have permission. Is this expected
behavior?