It's all about the answers!

Ask a question

Sprint Planning & Work Load


Chris Barlock (18814738) | asked Feb 25 '10, 1:04 p.m.
In my sprint planning, I have a user story with four child tasks:

A - 4 hours
B - 1 day
C - 2 days
D - 2 days

This totals 44 hours. If I open the story it says that the Progress is 0/84 hours! Where did the other 40 hours come from? Also, this story and tasks are currently planned for sprint 2 and RTC says my work load is overbooked by 36 hours. If I move just the story, not the four child tasks to sprint 3, now I'm underbooked by four hours -- the difference is the strange extra 40 hours. Can anyone explain this behavior?

Thanks!

Chris

Be the first one to answer this question!


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.