Work Load Question

We are using a four week sprint -- four 40-hour weeks gives you 160 hours for the sprint. We dedicate one week to test, so we have three weeks of dev time. So 160 * 0.75 = 120 dev hours. Then, we figure 70% effectiveness (email, stupid meetings, etc....), so 120 * 0.70 = 84 dev hours. So, I've taken 160 * (0.75 * 0.70) = 160 * 0.525.

If I open my user and set the work assignment load for the timeline to 53% (because you can't set 52.5%), my iteration plan shows that my max workload is 81 hours, not 84. I have to set 55% to force it to 84 hours. RTC bug, or am I missing something about how this is supposed to work?

Chris

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Feb 25 '10, 11:33 a.m.

Question was seen: 5,085 times

Last updated: Feb 25 '10, 11:33 a.m.

Confirmation Cancel Confirm