Please advise on the best method how to combine and consolidate multiple QM streams to single stream.

In the DOORs NG ETM project area, I am managing five Quality Management (QM) streams QM1, QM2, QM3, QM4, and QM5, which all belong to the same project area. I aim to consolidate these five QM streams into one final QM stream that will incorporate the consolidated content from all five streams. <o:p> </o:p>

<o:p>   </o:p>

The flow of content from each QM stream is as follows <o:p> </o:p>

<o:p>   </o:p>

QM1 Stream (Test Plan, Test Cases, Test Scripts) <o:p> </o:p>

QM2 Stream (Test Plan, Test Cases, Test Scripts) <o:p> </o:p>

QM3 Stream (Test Plan, Test Cases, Test Scripts) <o:p> </o:p>

QM4 Stream (Test Plan, Test Cases, Test Scripts) <o:p> </o:p>

QM5 Stream (Test Plan, Test Cases, Test Scripts) <o:p> </o:p>

<o:p>   </o:p>

To <o:p> </o:p>

<o:p>   </o:p>

QM Final Stream (Test Plan, Test Cases, Test Scripts). <o:p> </o:p>

<o:p>   </o:p>

The objective is to create a QM Final Stream that will compile all of the above into a single coherent structure <o:p> </o:p>

QM Final Stream (Test Plan, Test Cases, Test Scripts). <o:p> </o:p>

<o:p>   </o:p>

Once I successfully combine and consolidate the contents into the QM Final Stream, I intend to retain only this final stream i.e. QM Final Stream (Test Plan, Test Cases, Test Scripts), while deleting the existing QM streams (QM1, QM2, QM3, QM4, and QM5). <o:p> </o:p>

<o:p>   </o:p>

Please advise on the best method how to combine and consolidate multiple QM streams to single stream.

0 votes



One answer

Permanent link
I would test the following:
  • Create a 6th stream as a 'consolidation' stream.
  • When you want to merge changes into stream 6, baseline in the other streams (1-5) and then in stream 6 merge in the changes from those other stream baselines (give the baselines useful names to identify the stream and merge date/time).

Alternative would have been to keep the 5 plans in 1 stream and use test suites or master test plans to manage the allocation to different teams/disciplines.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,112

Question asked: Jul 28, 6:13 a.m.

Question was seen: 551 times

Last updated: Jul 29, 10:13 a.m.

Confirmation Cancel Confirm