Does Incremental Backup Supported for CLM
Currently, we are in the process of performing a complete backup of the CLM data. Due to the substantial size of the data, the backup process is taking longer than usual, resulting in an increased server downtime. Consequently, this situation is negatively affecting our business operations. Is there a possibility to implement incremental backups instead of full backups? |
One answer
Ralph Schoon (63.4k●3●36●46)
| answered Jun 25, 3:12 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER Incremental backups still require a full backup for the initial baseline.
|