Is there a way to "complete a sprint" in RTC/EWM?
In RTC/EWM, when you come to the end of a sprint, is there a way to indicate that you want to close the sprint and automatically move the uncompleted work items to either the next sprint (assuming that one has been defined) or to the backlog?
I am aware that you can manually move the uncompleted work items but I was checking to see if there was a feature of the tool that would allow me to close/complete/end the sprint and then identify where the uncompleted work items should go.
Accepted answer
Nothing automatic - this is because it's typically not an "all or nothing" type operation, as often you want to move some items to next sprint and some to backlog depending on your retro results.
I usually do this with the team during the retro, when you look at why you didn't accomplish what was planned and log any impediments. The hope is that you don't have very many items to move - if there are enough that automating it is even a question then that's pointing to a deeper issue and you would look at the sprint planning process