Is there a way to schedule the creation of Baselines in ERM Doors NExt 7.0.2?

 WE are not using GCM. I have been asked if there is a way to schedule baseline creations in ERM DNG, on different frequencies, or is the creation of baselines a manual process?


Thanks in advance.

Robyn

1

0 votes


Accepted answer

Permanent link

 To me, baselines have a meaning and a purpose. Usually baselines are manually created e.g. as a process step. I am not aware that you can set up a schedule to create baselines. It would be possible to use APIs to create baselines and run that on a schedule.

Robyn Riley selected this answer as the correct answer

1 vote

Comments

Thank you Ralph, I'm trying to explain that to the person who asked for this. He wants to be able to compare modules that have been changed. I suggested that he look at baselining once per week. Our staff recently moved from storing every artifact on SharePoint to using ERM and it's tough to change one's way of thinking.

 

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019

Question asked: Feb 21, 5:02 p.m.

Question was seen: 311 times

Last updated: Feb 23, 10:39 a.m.

Confirmation Cancel Confirm