Rollup estimates/progress


Sterling Ferguson-II (1.6k13288273) | asked Jun 02 '23, 2:04 p.m.
I am using a Formal template and have:
  • Defect
    • Task
    • Task
The two tasks have 8 hours and 3 hours. The first task has 2 hours spent. The plan shows the estimate and progress for the Tasks, but it is not rolled up to the Defect. Am I missing something? It's been awhile since I played with this planning feature...

Comments
Sterling Ferguson-II commented Jun 02 '23, 2:27 p.m.

Oddly enough, Progress does not show every after updating the Time Tracking piece.


Ralph Schoon commented Jun 13 '23, 10:10 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

Maybe you can provide screenshots? 

Accepted answer


permanent link
Sterling Ferguson-II (1.6k13288273) | answered Jun 13 '23, 3:38 p.m.

You can "resolve this". The "parent" work items were set as Plan items and not Execution items.

Ralph Schoon selected this answer as the correct answer