Bulk update work items - Calculated Value Attribute


Glyn Costello (1404554) | asked Jan 28 '22, 5:09 a.m.
Hi,

If a field that has a calculated value is updated via a query bulk update, how can I re-run the calculated value scripts on all updated work items?

I have already defined the "dependencies" in the calculated value attribute.

One answer



permanent link
Ralph Schoon (63.5k33646) | answered Jan 28 '22, 5:42 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

 https://jazz.net/wiki/bin/view/Main/AttributeCustomization#Calculated_values explains when calculated values run. As far as I can tell, you have to force a save of the work item, to get it re-calculated.   