It's all about the answers!

Ask a question

Bulk update work items - Calculated Value Attribute


Glyn Costello (13636) | asked Jan 28 '22, 5:09 a.m.
Hi,

If a field that has a calculated value is updated via a query bulk update, how can I re-run the calculated value scripts on all updated work items?

I have already defined the "dependencies" in the calculated value attribute.

One answer



permanent link
Ralph Schoon (63.1k33645) | answered Jan 28 '22, 5:42 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

 https://jazz.net/wiki/bin/view/Main/AttributeCustomization#Calculated_values explains when calculated values run. As far as I can tell, you have to force a save of the work item, to get it re-calculated.   

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.