KT PD (59310) | asked Jan 17 '22, 2:14 a.m.

 HI Team,


I am using Jazz Report Service version 6.0.6.1 for creating reports. I want to create project using "Lifecycle Query Engine scoped by configuration".
At the time of run report, I want to choose multiple configurations in "Chose a configuration" option.
Can you please help me to clarify , that we can able to choose multiple configurations in single project or need to create different report for each configuration.

Thanks

Accepted answer


permanent link
David Honey (1.8k17) | answered Jan 17 '22, 4:45 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

Re: I want to create project using "Lifecycle Query Engine scoped by configuration".

I assume you mean "I want to create a report using "Lifecycle Query Engine scoped by a configuration".

You cannot. A report against the "Lifecycle Query Engine scoped by a configuration" data source must be scoped to exactly one configuration. A report against multiple configurations is not supported and is likely to be meaningless. If you have multiple local configurations, you can add them as contributions to a global configuration and use that global configuration as the scope of a report.

KT PD selected this answer as the correct answer