 Hi, 


How do I upload a Report Resource (RPE template) for use in RQM for a Config-enabled project? 

The only options I have under "Reports" menu is "Create > From Resource, From Report Builder" but no option to add a resource. 

Thank you!

2 answers



permanent link
Subramanya Prasad Pilar (4.6k15) | answered Oct 02 '20, 11:13 a.m.
edited Oct 02 '20, 11:15 a.m.
Select Browse->Report Resources and you see an option "Create Resource" and you can upload the .dta file

permanent link
Glyn Costello (13636) | answered Oct 02 '20, 11:28 a.m.

 Hi, that option isn't available in the web browser, but I've found that I can upload using the Eclipse client. 